Mystic Way makeover is getting close. Fence is down!!
November 10, 2025 at 3:49 PM
McGrath highway creates terrible environments but I do love biking on Gilman St under McGrath on a sunny fall morning. Your eyes adjust to the shade, but then adjusts when you emerge, making the red leaves even more brilliant.
November 10, 2025 at 3:46 PM
October 29, 2025 at 1:03 PM
Bike valet at the end so the families can participate in Assembly row activities
October 26, 2025 at 11:07 PM
Volunteering to help with @familybikeride.bsky.social today.
October 26, 2025 at 3:42 PM
A few pictures from my bike ride (as transportation) yesterday; lovely way to get around on a fall day. 🥰 I wish I could have gotten a picture of my shadow on the green line tracks as I biked over the big hill between Lechmere and East Somerville.
October 26, 2025 at 2:52 PM
Making myself a Halloween costume out of things lying around.
October 25, 2025 at 1:59 PM
Does this look like a "gas gate" to anyone? I've logged 5 311 tickets about this pothole. I even left these directions: "Pothole in East bound bike lane, right before 3rd tree starting from the driveway to 90 Washington. To the left front of the bike lane arrow, at 5th flex post." 4 tickets closed.
October 24, 2025 at 7:15 PM
Q: describe what short piece is in rendering on Everett side?
A: stairs
A: the red part is actually pretty high and not at grade, 15' in the air where the stairs are.
57/?
October 22, 2025 at 12:21 AM
Q: benches on the bridge deck?
A: yes (see it in this rendering), and it's actually a bit wider there to accommodate the seating
47/?
October 22, 2025 at 12:03 AM
How to reach them:
submit email comments to mysticriverbikepedbridge@dot.state.ma.us

written comments can be submitted too
26/?
October 21, 2025 at 11:28 PM
Construction approach - using design build to combine design and construction services into a single contract

25/?
October 21, 2025 at 11:25 PM
Permitting statuses

24/?
October 21, 2025 at 11:23 PM
DCR is responsible for acquiring the needed right of way for permanent and temporary easements.

23/?
October 21, 2025 at 11:22 PM
Next steps: construction award start in Fall 2026, expecting completion fall/winter 2029

22/?
October 21, 2025 at 11:21 PM
New wider path, 18'. Rendering at night with lighting 21/?
October 21, 2025 at 11:21 PM
Bridge deck 20/?
October 21, 2025 at 11:19 PM
Main navigation span with view of 4 concrete legs
19/?
October 21, 2025 at 11:19 PM
Somerville side rendering 18/?
October 21, 2025 at 11:19 PM
Elevation view from downstream. Steel and concrete. The arch is at the navigation channel. 17/?
October 21, 2025 at 11:18 PM
On Everett side, the park will mostly stay open during construction 16/?
October 21, 2025 at 11:17 PM
A year after the park opens, they'll have to close off part of it to ensure safety during construction
15/?
October 21, 2025 at 11:17 PM
They've been coordinating with the Draw Seven Park team so the landing is being built

14/?
October 21, 2025 at 11:16 PM
Landing is still the same location, but now there are more detailed designs. Once Draw Seven is done, will be 8-12 minute walk around to get to Assembly Station (note: the new entrance to Assembly Station is out of scope - MBTA project)

13/?
October 21, 2025 at 11:15 PM
Emphasizing the reason for the alignments: needed to go under existing MBTA bridge, and over the water navigation channel

12/?
October 21, 2025 at 11:14 PM