Allison Bawden
banner
nukeoversight.bsky.social
Allison Bawden
@nukeoversight.bsky.social
Director for Nukes, GAO.
NNSA said it plans to implement new processes, including the use of templates and root cause guidance, to help project managers better meet reporting requirements. We recommend they complete the guidance and implement the process.
September 30, 2025 at 4:27 PM
NNSA saw costs grow >25% on 7 out of 14 construction projects, but didn’t notify Congress about 5 of them for months, let alone within the 30 days required by law. Nor did NNSA assess the root causes of cost overruns for those 5 within 90 days or inform Congress, as required. #nukesky
September 30, 2025 at 4:27 PM
Los Alamos looks forward to additional park-and-ride shuttle routes to the lab. NNSA has some concerns about potential challenges with having sufficient federal staff to oversee the program and assess whether it’s providing the intended benefits.
September 30, 2025 at 4:23 PM
Under a new authority in the FY25 NDAA, NNSA sites can reimburse some contractor commuting costs. This could improve safety and congestion. To date, Los Alamos is the only site to have made a proposal; they estimated it would cost $74 million to implement from FY25–30.
September 30, 2025 at 4:22 PM
Until the UPF is ready, NNSA will have to keep using an 80-year old facility that could cost up to a half billion dollars to maintain in the meantime. We recommended that NNSA develop a comprehensive plan for this maintenance.
September 18, 2025 at 5:04 PM
The UPF is also delayed. The agency is monitoring the project, but there are already doubts that the contractor will meet its project milestone for 2029. There are concerns about the ability to track project progress because of the way the contractor categorizes project tasks.
September 18, 2025 at 5:04 PM
The estimated cost to complete the UPF has increased nearly $4 billion just since construction started in 2018. Poor management accounts for $770 million of that. NNSA has conducted reviews to get to the root of the cost increases and implemented 19 out of 20 corrective actions.
September 18, 2025 at 5:03 PM
We are starting work on just this issue! Want to get to the root causes.
September 10, 2025 at 4:51 PM
As NNSA’s contractors underestimate the costs of the contracts across the enterprise, higher costs for small projects add up. We recommend NNSA ensure its contractors estimate costs more reliably to enable more realistic program planning & budgeting and better project management.
September 9, 2025 at 6:58 PM
Over the next 2 decades, the United States plans to spend tens of billions of dollars to modernize its nuclear weapons stockpile. These expenditures will include hundreds of millions of dollars a year in fixed-price construction subcontracts.
September 9, 2025 at 6:58 PM
NNSA’s plans for upgrading one of the facilities are no longer current and the agency hasn't evaluated its progress on repairing any of the three. We recommend that NNSA develop performance measures to track and report on its progress, and document options for future upgrades.
September 5, 2025 at 2:15 PM
In 2023 NNSA submitted to Congress a plan for repairing & upgrading these facilities. But the plan doesn’t give Congress—or other decision-makers, like NNSA management—all the information they need to determine whether the fusion facilities can continue to perform as designed.
September 5, 2025 at 2:15 PM
We pointed out some additional opportunities—for example, DNFSB should revise its human capital plan to include more details on how the Board will achieve its goals, and by when. This will support performance by ensuring that staff responsibilities are well defined.
September 4, 2025 at 3:49 PM
But! DNFSB is supposed to have 5 presidentially nominated & Senate-confirmed Board members. Filling seats has been challenging; as of August 2025, the Board had 2 seats filled, with 1 member’s term expiring in Oct 2025. With 1 seated member, the Board’s authority will be limited.
September 4, 2025 at 3:47 PM
There is a list on our web site of the unclassified titles of sensitive and classified (restricted) reports that we issue. It is regularly updated.
August 21, 2025 at 1:47 PM
I don't find classification to be an impediment to the work, but we aren't always able to issue our work publicly. Our preference is to issue our work publicly whenever possible, which sometimes means a public version in which we note the type of information that was removed for classification.
August 21, 2025 at 1:46 PM