Nathan Anderson
banner
atomicauditor.bsky.social
Nathan Anderson
@atomicauditor.bsky.social
Director of the U.S. Government Accountability Office's nuclear cleanup and environmental liabilities portfolio. Fly fisherman with strong ties to the Pacific Northwest.
Reposted by Nathan Anderson
Los Alamos looks forward to additional park-and-ride shuttle routes to the lab. NNSA has some concerns about potential challenges with having sufficient federal staff to oversee the program and assess whether it’s providing the intended benefits.
September 30, 2025 at 4:23 PM
Reposted by Nathan Anderson
Under a new authority in the FY25 NDAA, NNSA sites can reimburse some contractor commuting costs. This could improve safety and congestion. To date, Los Alamos is the only site to have made a proposal; they estimated it would cost $74 million to implement from FY25–30.
September 30, 2025 at 4:22 PM
Reposted by Nathan Anderson
NNSA said it plans to implement new processes, including the use of templates and root cause guidance, to help project managers better meet reporting requirements. We recommend they complete the guidance and implement the process.
September 30, 2025 at 4:27 PM
Reposted by Nathan Anderson
NNSA saw costs grow >25% on 7 out of 14 construction projects, but didn’t notify Congress about 5 of them for months, let alone within the 30 days required by law. Nor did NNSA assess the root causes of cost overruns for those 5 within 90 days or inform Congress, as required. #nukesky
September 30, 2025 at 4:27 PM
DOE also has opportunities to work with regulators on cost effectiveness. For example, DOE and California are still determining how to clean up soil at a site in Ventura County. DOE estimates that cleanup could cost between $57 million to $1 billion.
September 26, 2025 at 3:16 PM
We made the same recommendation to DOE in 2024 regarding groundwater cleanup—that the agency collect and use comprehensive information on groundwater cleanup to better prioritize. www.gao.gov/products/gao...
www.gao.gov
September 26, 2025 at 3:16 PM
More specific information about soil and legacy landfill cleanup from its sites would enable DOE to make better decisions on how to prioritize cleanup efforts across its sites, making the most of its limited resources.
September 26, 2025 at 3:16 PM
We recommend that DOE direct sites that haven’t completed an initial historical and current use review to do so by an established deadline and report to each responsible DOE office on whether additional investigation, characterization, or cleanup of PFAS contamination is needed.
September 24, 2025 at 3:05 PM
DOE found PFAS contamination in groundwater at Paducah, KY—up to 128,000 parts per trillion (ppt). No regulations currently limit PFAS in groundwater, but two PFAS types, PFOA and PFOS, are limited to 4 ppt in drinking water—about 1 drop in 5 Olympic-sized swimming pools.
September 24, 2025 at 3:05 PM
DOE has used PFAS—which has been linked to health issues like cancer and infertility—in firefighting foam and for uranium enrichment, among other things. These applications can release PFAS into the environment, but the extent of contamination is unknown.
September 24, 2025 at 3:05 PM
DOE has used PFAS—which has been linked to health issues like cancer and infertility—in firefighting foam and for uranium enrichment, among other things. These applications can release PFAS into the environment, but the extent of contamination is unknown.
September 24, 2025 at 3:01 PM
Reposted by Nathan Anderson
Until the UPF is ready, NNSA will have to keep using an 80-year old facility that could cost up to a half billion dollars to maintain in the meantime. We recommended that NNSA develop a comprehensive plan for this maintenance.
September 18, 2025 at 5:04 PM
Reposted by Nathan Anderson
The UPF is also delayed. The agency is monitoring the project, but there are already doubts that the contractor will meet its project milestone for 2029. There are concerns about the ability to track project progress because of the way the contractor categorizes project tasks.
September 18, 2025 at 5:04 PM
Reposted by Nathan Anderson
The estimated cost to complete the UPF has increased nearly $4 billion just since construction started in 2018. Poor management accounts for $770 million of that. NNSA has conducted reviews to get to the root of the cost increases and implemented 19 out of 20 corrective actions.
September 18, 2025 at 5:03 PM
Reposted by Nathan Anderson
Even so, there are signs that DNFSB is on the right track: DNFSB’s score on a measure of employee engagement & satisfaction jumped to 70 (out of 100) in 2024, from 39 in 2017. DNFSB’s primary resource is its people so better human capital planning means better outcomes.
September 4, 2025 at 3:48 PM
Even so, there are signs that DNFSB is on the right track: DNFSB’s score on a measure of employee engagement & satisfaction jumped to 70 (out of 100) in 2024, from 39 in 2017. DNFSB’s primary resource is its people so better human capital planning means better outcomes.
September 4, 2025 at 3:48 PM
Reposted by Nathan Anderson
But! DNFSB is supposed to have 5 presidentially nominated & Senate-confirmed Board members. Filling seats has been challenging; as of August 2025, the Board had 2 seats filled, with 1 member’s term expiring in Oct 2025. With 1 seated member, the Board’s authority will be limited.
September 4, 2025 at 3:47 PM