numble.bsky.social
@numble.bsky.social
I read LA Metro documents for fun.
LA Metro’s community meetings planned this week for Sepulveda Transit Corridor have been cancelled. According to what Nick Andert is hearing, there is a chance that LA Metro CEO Stephanie Wiggins may be trying to cancel the project.
I am hearing some, uh, VERY concerning things about the sepulveda line... trying to get more confirmation but it seems there's a chance Metro (presumably Stephanie Wiggins) is trying to wholly spike the project without releasing the EIR
April 1, 2025 at 9:45 PM
Reposted
I am hearing some, uh, VERY concerning things about the sepulveda line... trying to get more confirmation but it seems there's a chance Metro (presumably Stephanie Wiggins) is trying to wholly spike the project without releasing the EIR
April 1, 2025 at 9:35 PM
March 2025 LA Metro presentation on Link Union Station to Vernon stakeholders, focused on BNSF railroad improvements to facilitate project. Many transportation benefits now proposed for Vernon (maybe in response to city’s opposition to project).
www.linkunionstation.com
March 31, 2025 at 10:59 PM
March 2025 Metrolink presentation on results of schedule changes. 42.5k rides on Dodger Parade day. Off-peak ridership increased 60% while peak ridership decreased 1%. On-time performance dropped initially but is improving. Ridership is now 60% of Pre-COVID ridership.
March 31, 2025 at 7:04 PM
March 2025 LA Metro presentation on North Hollywood-Pasadena BRT. Details on alignment and adjustments to station locations. Construction expected to start late 2025/early 2026, to open for service in late 2027.

www.dropbox.com/scl/fo/lviaz...
March 28, 2025 at 7:05 PM
LA Metro’s camera-based bus lane enforcement program on two routes issued 5,500 tickets (total $1.6m in fines) in the first month, an increase from average of 570 tickets issued per month before camera-based enforcement.

laist.com/news/transpo...
March 28, 2025 at 5:14 PM
April 2025 LA Metro presentation on LA River Path project. Draft EIR coming this year, with board selection of alignment in 2026. Looking at 3 options. At least 46% of path would be elevated (where owners do not make enough land available).

www.dropbox.com/scl/fi/e7oph...
March 28, 2025 at 4:20 PM
February 2025 status report for LA Metro’s East San Fernando Valley (ESFV) line. Utility adjustments package 6 is 90% done, and work has started on package 4.
libraryarchives.metro.net/DPGTL/Status...
March 28, 2025 at 3:59 PM
February 2025 status report for LA Metro’s D Line Extension Section 3. 60.8% as of 2/28/25, +1.5% since 1/31/25.
libraryarchives.metro.net/DPGTL/Status...
March 28, 2025 at 3:57 PM
February 2025 status report for LA Metro’s D Line Extension Section 2. 73.5% as of 2/28/25, -3.2% since 1/31/25. Percentage decreased because $72m of extra work was added. Contractor added 7 days to forecast completion, now around mid/late November 2026.
libraryarchives.metro.net/DPGTL/Status...
March 28, 2025 at 3:55 PM
February 2025 status report on LAX Automated People Mover. 91.7% as of 2/22/25, +0.1% since 1/25/25. Percentages are misleading (change orders distort progress). Contractor added 28 days to estimated service date, now 2/9/26 instead of 1/12/26.
emma.msrb.org/P11833966-P1...
March 28, 2025 at 3:50 PM
February 2025 status report for LA Metro’s D Line Extension Section 1. 96.3% as of 2/28/25, +0.3% since 1/31/25. Contractor added 19 days to forecast completion, now 11/27/25 instead of 11/8/25.
libraryarchives.metro.net/DPGTL/Status...
March 28, 2025 at 3:47 PM
January 2025 status report for LA Metro’s East San Fernando Valley (ESFV) line. They finished negotiations and started work on 6 early work packages (out of 12 total).
libraryarchives.metro.net/DPGTL/Status...
March 28, 2025 at 10:12 AM
January 2025 status report for LA Metro’s D Line Extension Section 3. 59.3% as of 1/31/25, +1.5% since 12/27/24.
libraryarchives.metro.net/DPGTL/Status...
March 28, 2025 at 10:09 AM
January 2025 status report for LA Metro’s D Line Extension Section 2. 76.7% as of 1/31/25, +0.5% since 12/27/24. No change in forecast completion this month (around early/mid November 2026).
libraryarchives.metro.net/DPGTL/Status...
March 28, 2025 at 10:06 AM
January 2025 status report on LAX Automated People Mover. 91.7% as of 1/25/25, +0% since 12/28/25. Percentages are misleading (change orders distort progress). Contractor added 2 weeks to estimated service date (now 1/12/26 instead of 12/29/25).
emma.msrb.org/P21897139-P2...
March 28, 2025 at 10:00 AM
January 2025 status report for LA Metro’s D Line Extension Section 1. 96% as of 1/31/25, +0.3% since 12/27/24. Contractor added 30 days to forecast completion, now 11/8/25 instead of 10/9/25.
libraryarchives.metro.net/DPGTL/Status...
March 28, 2025 at 9:57 AM
December 2024 status report for LA Metro’s East San Fernando Valley (ESFV) line. Utility adjustment package 6 is almost finished.
libraryarchives.metro.net/DPGTL/Status...
March 28, 2025 at 9:53 AM
December 2024 status report for LA Metro’s D Line Extension Section 3. 57.7% as of 12/27/24, +0.6% since 11/29/24. Additional work (contract modifications) were added to contract, decreasing progress as percentage of contract value.
libraryarchives.metro.net/DPGTL/Status...
March 28, 2025 at 9:50 AM
December 2024 status report for LA Metro’s D Line Extension Section 2. 76.2% as of 12/27/24, +0.5% since 11/23/24. No change in forecast completion this month (around early/mid November 2026).
libraryarchives.metro.net/DPGTL/Status...
March 28, 2025 at 9:47 AM
December 2024 status report on LAX Automated People Mover. 91.7% as of 12/27/24, +5.2% since 11/23/24. Percentages are misleading (change orders distort progress). Contractor added 24 days to estimated service date (now 12/29/25 instead of 12/5/25).
emma.msrb.org/P11817716-P1...
March 28, 2025 at 9:44 AM
December 2024 status report for LA Metro’s D Line Extension Section 1. 95.7% as of 12/27/24, +0.3% since 11/29/24. Contractor added 11 days to forecast completion, now 10/9/25 instead of 9/28/25.
libraryarchives.metro.net/DPGTL/Status...
March 28, 2025 at 9:40 AM
November 2024 status report for LA Metro’s East San Fernando Valley (ESFV) line. 4 out of 12 early work packages have started, and they’ve finished negotiations on the next 2 early work packages.
libraryarchives.metro.net/DPGTL/Status...
March 28, 2025 at 9:36 AM
November 2024 status report for LA Metro’s D Line Extension Section 3. 57.1% as of 11/29/24, +0.5% since 10/26/24.
libraryarchives.metro.net/DPGTL/Status...
March 28, 2025 at 9:34 AM
November 2024 status report for LA Metro’s D Line Extension Section 2. 75.7% as of 11/29/24, +1% since 10/26/24. Contractor removed about 2 weeks to forecast completion, now around early/mid November 2026 instead of late November 2026.
libraryarchives.metro.net/DPGTL/Status...
March 28, 2025 at 9:30 AM